File #: 15-2433-1118    Name: ADA Final Pay
Type: Action Item Status: Passed
File created: 11/6/2015 In control: Board of Commissioners
On agenda: 11/18/2015 Final action: 11/18/2015
Title: FINAL PAYMENT: $72,704.12 ADA TRANSITION PLANS AT INDEPENDENCE, RUTHERFORD SAYRE, AND SHABBONA PARKS FRIEDLER CONSTRUCTION COMPANY SPECIFICATION NO. P-11004-059
Sponsors: Planning and Construction
Indexes: Final Payment
Attachments: 1. MBE-WBE Participation
November 18, 2015 - Board Meeting

Title
FINAL PAYMENT: $72,704.12
ADA TRANSITION PLANS AT INDEPENDENCE, RUTHERFORD SAYRE, AND SHABBONA PARKS
FRIEDLER CONSTRUCTION COMPANY
SPECIFICATION NO. P-11004-059

Body

To The Honorable Board of Commissioners of the Chicago Park District:

I. Recommendation

This is to certify that Friedler Construction Company on September 9, 2015 completed in a satisfactory manner and in full compliance with the terms and conditions of the contract, all work in connection with the ADA Transition Plans at Independence, Rutherford Sayre, and Shabbona Parks. The inspector approving final payment is Michael Fus.

It is therefore recommended that an order be approved for Final Payment in favor of Robe, Inc. in the amount of $72,704.12.

II. Final Payment Information

Vendor/Contractor: Friedler Construction Company
2525 N. Elston Ave., Suite D240
Chicago, IL 60647

Date of Notice to Proceed: August 28, 2013
Substantial Completion Date: September 8, 2014
Final Completion Date: October 22, 2015
Original Contract Amount: $ 3,474,800.00
Approved Change Orders: $ 160,406.19
Total Contract Amount $ 3,635,206.19
Aggregate Amount Paid to Date: $ 3,562,502.07
Amount of This Final Payment $ 72,704.12

Original Contract Amount Final Contract Amount Waived

MBE $869,000.00 (25.0%) $1,163,831.44 (32%) NO
WBE $176,200.00 (5.07%) $ 178,706.66 (5%) NO

III. Budget and Financial Information

Budget Classification: City (TIF), Capital Grant and SRA Bond

Funding code: 351.0001.0083.216005.NR001.G1.07.57151
351.0001.0127.216005.TF002.G1.08.56448
035.0001.0127.216005.SR081.01.01.56448

IV. Explanation

The Scope of Services for this project included accessibility improvements at three park sites: Independence, Rutherford Sayre, and Shabbona Parks.

At Independence, work included installation of a new elevator, reconstruction of the...

Click here for full text