FINAL PAYMENT: $72,704.12
ADA TRANSITION PLANS AT INDEPENDENCE, RUTHERFORD SAYRE, AND SHABBONA PARKS
FRIEDLER CONSTRUCTION COMPANY
SPECIFICATION NO. P-11004-059
Body
To The Honorable Board of Commissioners of the Chicago Park District:
I. Recommendation
This is to certify that Friedler Construction Company on September 9, 2015 completed in a satisfactory manner and in full compliance with the terms and conditions of the contract, all work in connection with the ADA Transition Plans at Independence, Rutherford Sayre, and Shabbona Parks. The inspector approving final payment is Michael Fus.
It is therefore recommended that an order be approved for Final Payment in favor of Robe, Inc. in the amount of $72,704.12.
II. Final Payment Information
Vendor/Contractor: Friedler Construction Company
2525 N. Elston Ave., Suite D240
Chicago, IL 60647
Date of Notice to Proceed: August 28, 2013
Substantial Completion Date: September 8, 2014
Final Completion Date: October 22, 2015
Original Contract Amount: $ 3,474,800.00
Approved Change Orders: $ 160,406.19
Total Contract Amount $ 3,635,206.19
Aggregate Amount Paid to Date: $ 3,562,502.07
Amount of This Final Payment $ 72,704.12
Original Contract Amount Final Contract Amount Waived
MBE $869,000.00 (25.0%) $1,163,831.44 (32%) NO
WBE $176,200.00 (5.07%) $ 178,706.66 (5%) NO
III. Budget and Financial Information
Budget Classification: City (TIF), Capital Grant and SRA Bond
Funding code: 351.0001.0083.216005.NR001.G1.07.57151
351.0001.0127.216005.TF002.G1.08.56448
035.0001.0127.216005.SR081.01.01.56448
IV. Explanation
The Scope of Services for this project included accessibility improvements at three park sites: Independence, Rutherford Sayre, and Shabbona Parks.
At Independence, work included installation of a new elevator, reconstruction of the west porch including removal of a deteriorated ComEd substation below the old porch and installation of new pole-mounted electrical transformers; new doors, hardware, signage, drinking fountains, new lockers and benches, companion restroom, path improvements, exterior benches, and accessible parking.
At Rutherford Sayre, work included construction of a new low-slope accessible route from grade level to the main porch and fieldhouse entrance and accessible parking. Additional improvements included selective tuck pointing repairs to the Fieldhouse.
At Shabbona, work included new accessible parking, installation of a new elevator, replacement of all lockers and benches, electrical and mechanical improvements, replacement of the Lobby reception desk, expansion of the Fitness Room, repairs to the existing exterior ramp at the main entrance, and construction of a new interior basement ramp creating an improved accessible route between the elevator, locker rooms and pool.