File #: 15-2387-0812    Name: Calumet Park Field House Renovation
Type: Action Item Status: Passed
File created: 8/3/2015 In control: Board of Commissioners
On agenda: 8/12/2015 Final action: 8/12/2015
Title: FINAL PAYMENT: $389,493.05 CALUMET PARK FIELD HOUSE RENOVATIONS TYLER LANE CONSTRUCTION SPECIFICATION NO. P-12032
Sponsors: Planning and Construction
Indexes: Final Payment
Attachments: 1. MBE-WBE-Tyler Lane

Title
FINAL PAYMENT: $389,493.05
CALUMET PARK FIELD HOUSE RENOVATIONS
TYLER LANE CONSTRUCTION
SPECIFICATION NO. P-12032

Body
To The Honorable Board of Commissioners of the Chicago Park District:

I. Recommendation

This is to certify that Tyler Lane Construction on May 7, 2015 completed in a satisfactory manner and in full compliance with the terms and conditions of the contract, all work in connection with Calumet Park - Field House Restorations. The project manager approving final payment is Jim McGreevy.

It is therefore recommended that an order be approved for Final Payment in favor of Tyler Lane Construction in the amount of $389,493.05.

II. Final Payment Information

Vendor/Contractor: Tyler Lane Construction
999 E. Touhy Ave., Suite 450
Des Plaines, IL 60018

Date of Notice to Proceed: July 1, 2013
Substantial Completion Date: October 2, 2014
Final Completion Date: May 7, 2015
Original Contract Amount: $ 2,500,473.00
Approved Change Orders: $ 224,765.82
Total Contract Amount $ 2,725,238.82
Aggregate Amount Paid to Date: $ 2,335,745.77
Amount of This Final Payment $ 389,493.05


Original Contract Amount Final Contract Amount Waived

MBE $600,000.00 (27%) $770,363.80 (28.3%) NO
WBE $190,000.00 (5.9%) $216,475.00 (7.94%) NO

III. Budget and Financial Information

Budget Classification: Capital
Fiscal Year: 2013-2014

Funding code: 037.8260.0011.627012.BD092.01.01.55131
040.0001.0011.216005.BD310.01.01.55131
060.0001.0011.216005.BD111.01.01.55131
070.8260.0011.627012.BD414.01.01.55131

IV. Explanation

The Scope of Services for this project included; roof replacement of all roofs, repairs to exterior concrete all around the building and repairs to interior water damaged finishes. Additional work included repairs to the underground drainage system at the field house and the removal of a deteriorated concrete chimney at the power h...