File #: 15-2387-0812    Name: Calumet Park Field House Renovation
Type: Action Item Status: Passed
File created: 8/3/2015 In control: Board of Commissioners
On agenda: 8/12/2015 Final action: 8/12/2015
Title: FINAL PAYMENT: $389,493.05 CALUMET PARK FIELD HOUSE RENOVATIONS TYLER LANE CONSTRUCTION SPECIFICATION NO. P-12032
Sponsors: Planning and Construction
Indexes: Final Payment
Attachments: 1. MBE-WBE-Tyler Lane

 

Title

FINAL PAYMENT:  $389,493.05

CALUMET PARK FIELD HOUSE RENOVATIONS

TYLER LANE CONSTRUCTION

SPECIFICATION NO. P-12032

 

Body

To The Honorable Board of Commissioners of the Chicago Park District:

 

I. Recommendation

 

This is to certify that Tyler Lane Construction on May 7, 2015 completed in a satisfactory manner and in full compliance with the terms and conditions of the contract, all work in connection with Calumet Park - Field House Restorations. The project manager approving final payment is Jim McGreevy.

 

It is therefore recommended that an order be approved for Final Payment in favor of Tyler Lane Construction in the amount of $389,493.05.

 

II. Final Payment Information

 

Vendor/Contractor:                       Tyler Lane Construction 

                     999 E. Touhy Ave., Suite 450

                     Des Plaines, IL 60018

 

Date of Notice to Proceed:                     July 1, 2013

Substantial Completion Date:                     October 2, 2014

Final Completion Date:                     May 7, 2015

Original Contract Amount:                       $ 2,500,473.00

Approved Change Orders:                     $    224,765.82

Total Contract Amount                     $ 2,725,238.82

Aggregate Amount Paid to Date:                     $ 2,335,745.77

Amount of This Final Payment                     $    389,493.05

 

 

Original Contract Amount                                          Final Contract Amount                     Waived

 

MBE                     $600,000.00   (27%)                       $770,363.80                     (28.3%)                     NO

WBE                       $190,000.00   (5.9%)                                  $216,475.00    (7.94%)                     NO

 

III. Budget and Financial Information

 

Budget Classification: Capital

Fiscal Year:                                            2013-2014

 

Funding code:                         037.8260.0011.627012.BD092.01.01.55131

040.0001.0011.216005.BD310.01.01.55131

060.0001.0011.216005.BD111.01.01.55131

070.8260.0011.627012.BD414.01.01.55131

 

IV. Explanation

 

The Scope of Services for this project included; roof replacement of all roofs, repairs to exterior concrete all around the building and repairs to interior water damaged finishes.  Additional work included repairs to the underground drainage system at the field house and the removal of a deteriorated concrete chimney at the power house.

 

 

VI. General Conditions

 

1) Conflicts: The Agreement shall not be legally binding on the Chicago Park District if entered into in violation of the provisions of 50 ILCS 105, the Public Officer Prohibited Activities Act.

 

2) Ethics: The Chicago Park District’s Ethics Code, Chapter III of the Code of the Chicago Park District, shall be incorporated into and made part of the agreement.

 

3) Contingent Liability:  Any agreement lawfully entered into for a period of more than one year shall be executory only for the amounts for which the Park District may become liable in succeeding fiscal years pursuant to 70 ILCS 1505/17(i).  The agreement shall contain a clause that any expenditure beyond the current fiscal year is subject to appropriation in the subsequent fiscal year budget.

 

4) Economic Disclosure Statement (“EDS”): Contractor may be subject to a full and complete EDS prior to execution of the contract.