Title
CHANGE ORDER NO. 01: $458,505.30
REVERE (PAUL) PARK FIELDHOUSE & CLUBHOUSE RESTORATION
STRUCTURES CONSTRUCTION LLC
SPECIFICATION NO. P-16008-027
Body
To: The Honorable Board of Commissioners of the Chicago Park District
I. Recommendation
Pursuant to Chapter XI, Section C, 4 of the Code of the Chicago Park District, it is recommended that a change order be approved affecting the contract for the subject work.
II. Award Information
Contractor: Structures Construction LLC.
2300 West Diversey
Chicago, IL. 60647
MBE% WBE%
Original Contract Amount: $4,495,386.00 25.82 5.09
Previous Change Orders: 0.00 0.00 0.00
Contract Amount Prior to This Change Order: $4,495,386.00 25.82 5.09
Amount of Current Change Order: $458,505.30 74.43 8.82
% of the Original Contract: 10.2%
New Contract Amount: $4,953,891.30 30.40 5.50
Contract Type: Construction Contract
Contract Period: Extended to September 30, 2022
Contract Amount: Not-to-exceed $4,953,891.30
Affirmative Action
Goals: The Minority- and Women-Owned Participation for this contract includes 25% Minority-Owned and 5% Women-Owned.
II. Award Information (Cont.)
Change Order No. 01:
This change order includes additional Carpentry, Finishes, Paving, Plumbing, Roofing and expenses resulting from a Stop Work Order (SWO) for the Revere Park Fieldhouse and Clubhouse Restoratio...
Click here for full text