Type: Action Item Status: Approved
File created: 8/26/2021 In control: Board of Commissioners
On agenda: 11/10/2021 Final action: 11/10/2021
Title: CHANGE ORDER NO. 01: NTE $4,000,000.00 CONSTRUCTION OF PARK 596 - ADMINISTRATION HEADQUARTERS, FIELDHOUSE AND SITE DEVELOPMENT PASCHEN ALL JOINT VENTURE SPECIFICATION NO. P-20015
Sponsors: Planning and Construction
Indexes: Change Order
Attachments: 1. Updated MBE and WBE Schedules
TITLE

CHANGE ORDER NO. 01: NTE $4,000,000.00
CONSTRUCTION OF PARK 596 - ADMINISTRATION HEADQUARTERS, FIELDHOUSE AND SITE DEVELOPMENT
PASCHEN ALL JOINT VENTURE
SPECIFICATION NO. P-20015

Body
To the Honorable Board of Commissioners of the Chicago Park District

I. Recommendation

It is recommended that a change order be approved affecting the contract for the subject work; said change to authorize:

Change Order #01: Construction scope of work changes associated with additional building undercuts, additional site undercuts, removal of unforeseen concrete slabs and foundations, and removal of unforeseen underground storage tanks.

ADD: Not-to-Exceed $4,000,000.00

II. Change Order Information

Contractor: Paschen All Joint Venture

F.H. Paschen, S.N. Nielsen & Associates LLC
5515 N. East River Road
Chicago, IL 60656

All Construction Group
1425 S. 55th Court
Cicero, IL 60804






MBE%

WBE%
Original Contract Amount :
$64,505,650.00
37.53
6.64
Previous Change Orders :
$ 0.00
-
-
Contract Amount prior to this Change Order:
$64,505,650.00
37.53
6.64
Amount of Current Change Order:
$ 4,000,000.00 (6.20%)
0.00*
0.00*
New Contract Amount:
$68,505,650.00
35.34
6.25

Contract Type: Construction Contract

Contract Period: Contract time will remain the same

Contract Amount: Not-to-Exceed $68,505,650.00

*This change order includes work by MBE contractor Efficient Trucking and WBE contractor Katco Development. The Contractor will maintain the minimum 26.00% MBE and 6.00% WBE compliance on this contract. Once change order work has been completed, the Contractor will reconcile the actual MBE/WBE dollar participation by sub-contractor and provide Chicago Park District Purchasing Department with updated Schedule A's and B's. Again, per the contract, the contractor will retain 26.00% / 6.00% MBE/WBE ratios throughout the job.

Change Order #01: Additional building undercuts were required in the footprint of the new administrative buildi...