File #: 15-2341-0610    Name: Park 574 Final Payment
Type: Action Item Status: Passed
File created: 6/1/2015 In control: Board of Commissioners
On agenda: 6/10/2015 Final action:
Title: FINAL PAYMENT: $126,110.02 2540 W. JACKSON BLVD PARK #574 DEVELOPMENT ALL-BRY SPECIFICATION NO. P-11004-051R
Sponsors: Planning and Construction
Indexes: Final Payment
Attachments: 1. MWBE-All-Bry (Park 574)
Title
FINAL PAYMENT:  $126,110.02
2540 W. JACKSON BLVD
PARK #574 DEVELOPMENT
ALL-BRY
SPECIFICATION NO. P-11004-051R
 
Body
To The Honorable Board of Commissioners of the Chicago Park District:
 
I. Recommendation
 
This is to certify that All-Bry Construction Company on May 26, 2015 completed in a satisfactory manner and in full compliance with the terms and conditions of the contract, all work in connection with Park #574 Development.  The inspector approving final payment is Steffan Schoenauer.
 
It is therefore recommended that an order be approved for Final Payment in favor of All-Bry Construction Company in the amount of $126,110.02.
 
II. Final Payment Information
 
Vendor/Contractor:        All-Bry Construction Company
145 Tower Drive Suite 7
Burr Ridge, IL 60527
 
Date of Notice to Proceed:      September 30, 2013
Substantial Completion Date:      September 30, 2014
Final Completion Date:      May 26, 2015
Original Contract Amount:        $2,200,400.00
Approved Change Orders:      $     68,203.30
Total Contract Amount      $2,268,603.30
Aggregate Amount Paid to Date:      $2,142,493.28
Amount of This Final Payment      $  126,110.02
 
Original Contract Amount            Final Contract Amount      Waived
 
MBE      $600,000.00 (27.3%)      $834,725.00 (36.8%)      NO
WBE        $118,688.00(5.4%)       $115667.00 (5.1%)      NO
 
III. Budget and Financial Information
 
Budget Classification:       Capital
Fiscal Year:       2013
Funding code:      351.8260.0574.627030.IF001.G2.08.55149
 
IV. Explanation
 
The Park District will develop a 2.27 acre vacant site adjacent to the Chicago Housing Authority's Rockwell Gardens  into a new outdoor active recreation park within Chicago's Near West Side Community area that has a growing residential population. The new park was part of a land exchange with the CHA that was previously approved by the Board on August 13, 2008. Before transfer, W. Adams Street was legally vacated between S.Rockwell Street on the north and S. Maplewood Street on the south creating the contiguous footprint for park development.
 
The newly developed park will include a state of the art flagship playground that will service the immediate local community and regional community at large. Features of this playground include challenging, interactive playground equipment, rubberized soft surfacing with varied topography throughout the active play areas, drinking fountain, seat walls and picnic tables. The park elements include fencing, pedestrian pathways, a walking trail with exercise equipment stations, landscaping - ornamental and shade trees, sod and shrubs, lighting and all underground utilities.  
 
 
VI. General Conditions
1) Conflicts: The Agreement shall not be legally binding on the Chicago Park District if entered into in violation of the provisions of 50 ILCS 105, the Public Officer Prohibited Activities Act.
 
2) Ethics: The Chicago Park District's Ethics Code, Chapter III of the Code of the Chicago Park District, shall be incorporated into and made part of the agreement.
 
3) Contingent Liability:  Any agreement lawfully entered into for a period of more than one year shall be executory only for the amounts for which the Park District may become liable in succeeding fiscal years pursuant to 70 ILCS 1505/17(i).  The agreement shall contain a clause that any expenditure beyond the current fiscal year is subject to appropriation in the subsequent fiscal year budget.
 
4) Economic Disclosure Statement ("EDS"): Contractor may be subject to a full and complete EDS prior to execution of the contract.