To: The Honorable Board of Commissioners of the Chicago Park District
I. Recommendation
Pursuant to Chapter XI, Section C, 4 of the Code of the Chicago Park District, it is recommended that a change order be approved affecting the contract for the subject work.
Change Order #01: Contractor to provide additional construction services for the expansion of the artificial turf baseball infield, installation of a playground, resurfacing of the existing asphalt walking path. ADD $498,621.00
II. Award Information
Vendor/Contractor: Friedler Construction Corporation
2525 N. Elston Aver D-240
Chicago, IL 60647
MBE%
WBE%
Original Contract Amount :
$1,546,800.00
25 %
5 %
Previous Change Order :
$0
0 %
0 %
Contract Amount prior to this Change Order
$1,546,800.00
25 %
5 %
Amount of Current Change Order :
$ 498,621.00
25.0 %
8.6 %
% of the Original Contract
32.2%
New Contract Amount:
$2,045,421.00
25.0 %
5.3 %
Contract Type: Construction Services
Contract Period: Contract time will be extended to June 1, 2015
Contract Amount: Not-to-exceed $2,045,421.00
Affirmative Action
Goals: The Minority- and Women-Owned Participation for this contract includes 25% Minority-Owned and 5.3% Women-Owned.
II. Award Information (Cont.)
Change Order #01:
This change order includes converting the baseball infield to artificial turf rather than typical infield mix as originally bid. Scope also includes installation of a new playground as well as renovation of the existing pathway on the south side of the park. Work will require additional services for demolition, excavation, sewer, base preparation, installation of artificial turf, fencing, playground timbers and equipment, engineered wood fibar, grinding of existing asphalt and asphalt resurfacing.
The MBE portion of this change order will be performed by Martinez Frog Inc for material haul off and delivery ...
Click here for full text