File #: 26-1291-0408    Name: Request to extend the target market contract with DuSable Design Alliance for DuSable Park Development, P-21009, for two years and approve change order no. 3
Type: Action Item Status: New Business
File created: 3/16/2026 In control: Board of Commissioners
On agenda: 4/8/2026 Final action:
Title: REQUEST TO EXTEND THE TARGET MARKET CONTRACT WITH DUSABLE PARK DESIGN ALLIANCE FOR DUSABLE PARK DEVELOPMENT SPECIFICATION NO. P-21009 FOR TWO YEARS AND APPROVE CHANGE ORDER NO. 3
Sponsors: Planning and Construction
Indexes: Change Order
Attachments: 1. MWBE Schedules - DuSable Park Design Alliance
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TITLE

REQUEST TO EXTEND THE TARGET MARKET CONTRACT WITH DUSABLE PARK DESIGN ALLIANCE FOR DUSABLE PARK DEVELOPMENT SPECIFICATION NO. P-21009 FOR TWO YEARS AND APPROVE CHANGE ORDER NO. 3

BODY
To: The Honorable Board of Commissioners of the Chicago Park District

I. Recommendation

Pursuant to Chapter XI, Section C.3.a of the Code of the Chicago Park District, the Director of Purchasing and the Director of Planning & Development recommend, notwithstanding the lack of complete Economic Disclosure Statements, that the Board of Commissioners of the Chicago Park District (the "Board") authorize a two (2) year extension of the DuSable Park Development Design Services Agreement dated as of September 1, 2022 and approve Change Order No. 3 in an amount not to exceed $387,021.00 for Specification No. P-21009 (the "Project") for construction administration services to be provided by DuSable Park Design Alliance.


II. Award Information

Date of Award: March 9, 2022

Contractor: DuSable Park Design Alliance
2301 South Michigan Avenue
Chicago, IL 60616
MBE% WBE%
Original Contract Amount : $1,570,000.00 49.81 25.71
Previous Change Orders (#01-#02): $ 913,882.00 - -
Contract Amount prior to this Change Order: $2,483,882.00 47.22 25.44
Amount of Current Change Order (#03): $387,021.00 (24.65%) 49.62 31.39
Total Change Order Value (#01-#03): $1,300,903.00 (82.86%) - -
Total New Contract Amount: $2,870,903.00 48.07 26.24

Company Type: Joint Venture

Majority Interest: Brook Architecture 51% interest
Ross Barney Architects 49% interest

New Contract Amount: Not-to-exceed $2,870,903.00

Compliance Goals: The Minority and Women-Owned Participation for this contract includes 48.07% Minority-Owned and 26.24% Women Owned participation.

Contract Period: One (1) year initial term with four (4) one (1) year extension options. The contract will expire on August 31, 2028.

Scope of Services: Construction Administration and Observation.

Authorization: Authori...