Title
AUTHORIZATION TO ENTER INTO AGREEMENTS WITH CONTRACTORS FOR INCLUSION IN THE RAPID RESPONSE CONSTRUCTION SERVICES
PRE-QUALIFIED POOL
SPECIFICATION NO. P-22015
Body
To the Honorable Board of Commissioners of the Chicago Park District
I. Recommendation
It is recommended that the General Superintendent and CEO or the designee enter into individual agreements with sixteen (16) contractors for inclusion in the Rapid Response Construction Services pre-qualified pool. The pre-qualified contractors were selected pursuant to a publicly advertised Request for Qualification (RFQ). No minimum amount of work is required or guaranteed to the contractors in the pre-qualified pool. Each contractor must enter into an agreement for inclusion in the pre-qualified pool, and once in the pool, no work may commence and no payment shall be made until contractor is awarded a project and receives a Notice-to-Proceed from the Chicago Park District (CPD).
II. Award Information
Contractors: Sixteen (16) pre-qualified contractors as listed on Exhibit A (attached and incorporated by this reference)
Contract Type: Term Agreement
Contract Term: Five (5) year contract term expiring on December 31, 2028 with one (1) additional one (1) year extension
Contract Amount: Funding shall be based upon annual appropriations
Scope of Services: Generally, projects for this pre-qualified pool may involve both building or park construction and renovation, and some projects may involve both. Specific scope could include roofing, masonry, mechanical, electrical, plumbing, architectural finishes and general carpentry, ADA compliance upgrades, pool systems, windows, doors, hardware, signage, paving, landscaping, utilities, water parks/spray pools, athletic fields, playgrounds, park monuments, sport courts, park structures, fencing.
Affirmative
Action Goals: Per the RFQ, MBE and WBE participation may not always be achievable on every individual IFB package issued to the Rapid Response C...