File #: 22-1041-0608    Name: Change Order for Jackson Park Track and Field
Type: Action Item Status: Passed
File created: 3/23/2022 In control: Board of Commissioners
On agenda: 6/8/2022 Final action: 6/8/2022
Title: CHANGE ORDER NO. 01: $370,083.10 JACKSON PARK TRACK & FIELD CHICAGO COMMERCIAL CONSTRUCTION SPECIFICATION NO. P-16008-010
Sponsors: Planning and Construction
Indexes: Change Order
Attachments: 1. Chicago Commercial Construction - Updated MWBE Schedules
Title

CHANGE ORDER NO. 01: $370,083.10
JACKSON PARK TRACK & FIELD
CHICAGO COMMERCIAL CONSTRUCTION
SPECIFICATION NO. P-16008-010

Body
To the Honorable Board of Commissioners of the Chicago Park District

I. Recommendation

It is recommended that a change order be approved affecting the contract for the subject work; said change to authorize:

Change Order #01: Material and labor escalation costs as well as construction scope of work changes associated with changes to the water main service connection, changes to the sanitary service, additional tree planting, temporary fencing and costs for a donor recognition plaque.

ADD: $370,083.10

II. Change Order Information

Contractor: CCC Holdings, Inc.
dba Chicago Commercial Construction
18660 Graphics Drive, Suite 200
Tinley Park, IL 60477




MBE%
WBE%
Original Contract Amount:
$ 3,751,000.00
40.52
5.87
Previous Change Orders:
$ 0.00
-
-
Contract Amount prior to Change Order:
$ 3,751,000.00
42.74
13.76
Amount of Current Change Order:
$ 370,083.10 (9.87%)
68.04
0.00
New Contract Amount:
$ 4,121,083.10
45.01
6.06

Contract Type: Construction Contract

Contract Period: Contract time will remain the same

Contract Amount: $ 4,121,083.10

This change order includes work by MBE contractor CPMH for $252,017.73. The Contractor will maintain the minimum 25.00% MBE and 5.00% WBE compliance on this contract.


Change Order #01: Material and labor escalation costs as well as construction scope of work changes associated with changes to the water main service connection, changes to the sanitary service, additional tree planting and costs for a donor recognition plaque.

Material and labor escalation costs were experienced on the project due to a nearly three year work stoppage. Construction proposals were received on June 13, 2018 and construction initially began in...