TITLE
CHANGE ORDER NO. 01: NTE $587,633.18
CONSTRUCTION OF THE GARFIELD PARK CONSERVATORY ELIZABETH MORSE GENIUS CHILDREN'S GARDEN
FH PASCHEN
SPECIFICATION NO. P-23007
BODY
To the Honorable Board of Commissioners of the Chicago Park District
I. Recommendation
It is recommended that a change order be entered authorizing the General Superintendent or designee to enter into an agreement with F.H. Paschen, S.N. Nielsen & Associates LLC for additional construction services for the development of the Garfield Park Conservatory Elizabeth Morse Genius Children's Garden for the subject services described below:
Change Order #01: Construction scope of additional work associated with the purchase and installation of two playground features included as Alternates in the original project bid. Additional work associated with Alternate 2 "Pitcher Plant Perch" and Alternate 3 "Recharge Arbor" includes concrete foundation, structural steel, structural steel erection, handrails painting, subgrade excavation, electrical, root arbor sculpture and benches. This additional work is funded through private donations through the Garfield Park Conservatory Alliance.
ADD: Not-to-Exceed $587,633.18
II. Change Order Information
Contractor: F.H. Paschen, S.N. Nielsen & Associates LLC
5515 N. East River Road
Chicago, IL 60656
MBE%
WBE%
Original Contract Amount:
$8,581,000.00
26.4
6.00
Previous Change Orders:
$0.00
-
-
Contract Amount prior to this Change Order:
$8,581,000.00
26.4
6.00
Amount of Current Change Order:
$587,633.18 (6.8%)
8.9
30.1
New Contract Amount:
$9.168.633.18
25.29
7.57
Contract Type: Construction Contract
Contract Period: Contract time will remain the same
Contract Amount: Not-to-Exceed $9,168,633.18
*This change order includes work by MBE contractor Pinto, Legend, Evans and WBE contractor Dian, R.W. Collins. The Contractor will maintain the minimum 25.00% MBE and 5.00% WBE compliance on this contract. Once change order work has been ...
Click here for full text