Chicago Park District Site Banner

File #: 24-1013-0124    Name: Change Order to Pacific Construction Services LLC for Clarendon Park Community Center Renovation
Type: Action Item Status: Passed
File created: 12/22/2023 In control: Board of Commissioners
On agenda: 1/24/2024 Final action: 1/24/2024
Title: CHANGE ORDER NO. 05: TO PACIFIC CONSTRUCTION SERVICES LLC FOR THE CLARENDON COMMUNITY CENTER RENOVATION SPECIFICATION NO. P16008-050
Sponsors: Planning and Construction
Indexes: Change Order
Attachments: 1. MWBE Schedules - Pacific Construction
TITLE

CHANGE ORDER NO. 05:
TO PACIFIC CONSTRUCTION SERVICES LLC
FOR THE CLARENDON COMMUNITY CENTER RENOVATION
SPECIFICATION NO. P16008-050

BODY
To the Honorable Board of Commissioners of the Chicago Park District

I. Recommendation

It is recommended that a change order be approved affecting the contract for the subject work, said change to authorize:

Change Order #05: Additional expenses associated with a project time extension. This is a result of having to resolve various complex discovered conditions during construction that added additional time to the construction schedule at this more than 100-year-old historic building.

ADD: $324,073.75


II. Change Order Information

Contractor: Pacific Construction Services LLC
5511 N. Cumberland Ave., Suite 608
Chicago, IL. 60656

MBE% WBE%
MBE% WBE%
Original Contract Amount: $12,877,092.00 25.00 5.49
Previous Change Orders (#01-#04): $688,317.65 (5.35%) 16.52 14.48
Contract Amount prior to this Change Order: $13,565,409.65 39.88 6.08
Amount of Current Change Order #05: $324,073.75 (2.52%) 1.06 0.00
Total Aggregate Change Order Value (#01-#05): $1,012,391.40 (7.86%) 11.57 9.84
New Contract Amount: $13,889,483.40 38.97 5.94


Contract Type: Construction

Contract Period: Time Extension to June 12, 2024

Contract Amount: Not-to-exceed $13,889,483.40

This change order incl...