Chicago Park District Site Banner

File #: 24-1111-0710    Name: Change Order #1 to Industria Inc. for Garfield Park Bandstand Rehabilitation, Specification No. P-16008-059
Type: Action Item Status: Passed
File created: 6/14/2024 In control: Board of Commissioners
On agenda: 7/10/2024 Final action: 7/10/2024
Title: AUTHORIZATION TO APPROVE CHANGE ORDER #01 TO INDUSTRIA, INC., FOR GARFIELD PARK BANDSTAND REHABILITATION SPECIFICATION NO. P-16008-059
Sponsors: Planning and Construction
Indexes: Change Order
Attachments: 1. MWBE Schedules - Industria Inc.
Title

AUTHORIZATION TO APPROVE CHANGE ORDER #01 TO INDUSTRIA, INC., FOR GARFIELD PARK BANDSTAND REHABILITATION
SPECIFICATION NO. P-16008-059

Body
To the Honorable Board of Commissioners of the Chicago Park District

I. Recommendation

It is recommended that a change order be approved affecting the contract for the subject work, said change to authorize:

Change Order #01: Additional expenses are identified to address significant unanticipated structural deficiencies at this 128-year-old historic building. This change order also includes a time extension for the strategic implementation of temporary shoring required for the structural masonry repairs.

ADD: $1,132,151.27

II. Change Order Information

Contractor: Industria, Inc.
2860 S. River Road, Suite 100
Des Plaines, IL. 60018
MBE% WBE%
Original Contract Amount: $ 2,286,390.00 28.28 7.74
Amount of Current Change Order #01: $ 1,132,151.27 (49.52%) 43.75 31.28
New Contract Amount: $3,418,541.27 33.40 15.54

Contract Period: Time Extension to March 31, 2025

Contract Amount: Not-to-exceed $3,418,541.27

This change order includes: $495,276.00 MBE participation by W.B.F. Construction; and $354,180.00 WBE participation by M.B.B. Enterprises of Chicago, Inc. Overall project participation including this Change Order is at 33.40% MBE and at 15.54% WBE. The Contractor will continue to meet or exceed the minimum 25.00% MBE and 5.0% WBE compliance on this contract.

Change Order #01:

The original project scope for this rehabilitation project identified removal, repairs and reinstallation of all exterior marble cladding that was observed to have shifted out of alignment. Archival documents did not provide explicit information on the structural support system of the bandstand. A limited amount of ma...