TITLE
CHANGE ORDER NO. 02: $1,249,107.00
TO PASCHEN ALL JOINT VENTURE FOR CONSTRUCTION OF PARK 596 - ADMINISTRATION HEADQUARTERS, FIELDHOUSE AND SITE DEVELOPMENT
SPECIFICATION NO. P-20015
Body
To the Honorable Board of Commissioners of the Chicago Park District
I. Recommendation
It is recommended that a change order be approved affecting the contract for the subject work; said change to authorize:
Change Order #02: Construction scope of work changes due to permit-required modifications to the traffic signal plans and extended general conditions.
ADD: $1,249,107.00
II. Change Order Information
Contractor: Paschen All Joint Venture
F.H. Paschen, S.N. Nielsen & Associates LLC
5515 N. East River Road
Chicago, IL 60656
All Construction Group
1425 S. 55th Court
Cicero, IL 60804
MBE% WBE%
Original Contract Amount: $64,505,650.00 37.53 6.64
Previous Change Orders (CO#01): $ 4,000,000.00 (6.20%) 0.00 0.00
Contract Amount prior to this Change Order: $68,505,650.00 35.34 6.25
Unspent Amount to date of CO#01 $(2,035,301.00) (-2.97%)
Amount of Current Change Order: $ 1,249,107.00 (1.94%) - -
Total Change Order Value (CO#01-02) $ 3,213,806.00 (4.98%) 0.00 0.00
New Contract Amount: $67,719,456.00 38.7 8.3
Contract Type: Construction Contract
Contract Period: Schedule exclusively for this Change Order work as negotiated.
Contract Amount: $67,719,456.00
This change order includes work by MBE contractor Natural Creations. The Contractor will maintain the minimum 26.00% MBE and 6.00% WBE compliance on this contract.
Change Order #02: Construction scope of work changes due to permit-required modifications to the traffic signal plans and extended general conditions.
As a part of the Planned Development for Park 596, a new traffic signal at the intersection of S. Western Avenue and W. 48th Place was required. Western Avenue is under the jurisdiction of the Illinois Department of Transportation (IDOT) but is maintained by the City of Chicag...
Click here for full text