File #: 25-1089-0514    Name: Change Order to Paschen All Joint Venture for Construction of Park 596, Specification No. P-20015
Type: Action Item Status: New Business
File created: 4/7/2025 In control: Board of Commissioners
On agenda: 5/14/2025 Final action:
Title: CHANGE ORDER NO. 02: $1,249,107.00 TO PASCHEN ALL JOINT VENTURE FOR CONSTRUCTION OF PARK 596 - ADMINISTRATION HEADQUARTERS, FIELDHOUSE AND SITE DEVELOPMENT SPECIFICATION NO. P-20015
Sponsors: Planning and Construction
Indexes: Change Order
Attachments: 1. MWBE Schedules - Paschen All Joint Venture
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TITLE

CHANGE ORDER NO. 02: $1,249,107.00
TO PASCHEN ALL JOINT VENTURE FOR CONSTRUCTION OF PARK 596 - ADMINISTRATION HEADQUARTERS, FIELDHOUSE AND SITE DEVELOPMENT
SPECIFICATION NO. P-20015

Body
To the Honorable Board of Commissioners of the Chicago Park District

I. Recommendation

It is recommended that a change order be approved affecting the contract for the subject work; said change to authorize:

Change Order #02: Construction scope of work changes due to permit-required modifications to the traffic signal plans and extended general conditions.
ADD: $1,249,107.00


II. Change Order Information

Contractor: Paschen All Joint Venture

F.H. Paschen, S.N. Nielsen & Associates LLC
5515 N. East River Road
Chicago, IL 60656

All Construction Group
1425 S. 55th Court
Cicero, IL 60804
MBE% WBE%
Original Contract Amount: $64,505,650.00 37.53 6.64
Previous Change Orders (CO#01): $ 4,000,000.00 (6.20%) 0.00 0.00
Contract Amount prior to this Change Order: $68,505,650.00 35.34 6.25
Unspent Amount to date of CO#01 $(2,035,301.00) (-2.97%)
Amount of Current Change Order: $ 1,249,107.00 (1.94%) - -
Total Change Order Value (CO#01-02) $ 3,213,806.00 (4.98%) 0.00 0.00
New Contract Amount: $67,719,456.00 38.7 8.3

Contract Type: Construction Contract

Contract Period: Schedule exclusively for this Change Order work as negotiated.

Contract Amount: $67,719,456.00

This change order includes work by MBE contractor Natural Creations. The Contractor will maintain the minimum 26.00% MBE and 6.00% WBE compliance on this contract.

Change Order #02: Construction scope of work changes due to permit-required modifications to the traffic signal plans and extended general conditions.

As a part of the Planned Development for Park 596, a new traffic signal at the intersection of S. Western Avenue and W. 48th Place was required. Western Avenue is under the jurisdiction of the Illinois Department of Transportation (IDOT) but is maintained by the City of Chicag...