Title
CHANGE ORDER #1
NORTHERLY ISLAND PARK
NORTHERLY ISLAND HABITAT PROJECT
ARMY CORPS OF ENGINEERS
CIP # 57258
Body
To: The Honorable Board of Commissioners of the Chicago Park District
I. Recommendation
Pursuant to Chapter XI, Section C, 4 of the Code of the Chicago Park District, it is recommended that a change order be approved affecting the contract for the subject work.
II. Award Information
Vendor/Contractor: Army Corps of Engineers
Chicago District
231 South LaSalle Street, Suite 1500
Chicago, IL 60604
CPD
Original Contract Amount : $2,596,520
Previous Change Order :|9 13|
Contract Amount prior to this Change Order $2,596,520
Amount of Current Change Order : $650,300
% of the Original Contract 25%
New Contract Amount: $3,246,820
Contract Type: Construction
Contract Period: September 2012 to November 2017
Contract Amount: $3,246,820
II. Award Information (Cont.)
Change Order #1:
A change order at Northerly Island is needed to address flooding issues created by waves overtopping from Lake Michigan. Excavation has also unearthed the original timber crib revetment from the time of the 1933 World's Fair. The additional funding will be used to increase the height of the lakefront revetment, build cobble shoots to direct wave action into the newly created pond, and to build overlooks adjacent to the timber crib revetment.
Authorization: Authorize the General Counsel to include other relevant terms and conditions in the written Agreement. Authorize the General Superintendent to execute the Agreement and the Secretary to attest as to the signing of the Agreement and keep an original copy of the Agreement on file.
III. Budget and Financial Information
Park Location: Northerly Island
Specification Number: N/A CIP 57258
Budget Classification: Capital
Fiscal Year: 2014
Source of Funds: 015.8260.0034.623020.NI001.01.01.57258
IV. Explanation
Sec...