File #: 22-1007-0216    Name: Change order Seward Park
Type: Action Item Status: Approved
File created: 1/10/2022 In control: Board of Commissioners
On agenda: 2/16/2022 Final action: 2/16/2022
Title: CHANGE ORDER NO. 02: $798,585.02 SEWARD PARK FIELDHOUSE RESTORATION FRIEDLER CONSTRUCTION COMPANY SPECIFICATION NO. P-16008-036
Sponsors: Planning and Construction
Indexes: Change Order
Title

CHANGE ORDER NO. 02: $798,585.02
SEWARD PARK FIELDHOUSE RESTORATION
FRIEDLER CONSTRUCTION COMPANY
SPECIFICATION NO. P-16008-036

Body

To: The Honorable Board of Commissioners of the Chicago Park District

I. Recommendation

Pursuant to Chapter XI, Section C, 4 of the Code of the Chicago Park District, it is recommended that a change order be approved affecting the contract for the subject work.

II. Award Information

Contractor: Friedler Construction Company
1001 N. Milwaukee, Suite 402
Chicago, IL. 60642

MBE% WBE%
Original Contract Amount: $2,270,800.00 25.41 5.73
Previous Change Orders: $88,694.93 23.27 0.00
Contract Amount prior to this Change Order: $2,359,494.93 25.33 5.51
Amount of Current Change Order: $798,585.02 24.24 6.26
% of the Original Contract: 35%
New Contract Amount: $3,158,079.95 25.06 5.70


Contract Type: Construction Contract

Contract Period: Extended to May 9, 2022

Contract Amount: Not-to-exceed $3,158,079.95

Affirmative Action
Goals: The Minority- and Women-Owned Participation for this contract includes 25% Minority-Owned and 5% Women-Owned.





II. Award Information (Cont.)

Change Order No. 02:

This Change Order includes extensive repair and replacement of deteriorated infrastructure discovered during demolition that wouldn't have been known at the time the construction documents were created until walls and floors were opened up and excavation started w...

Click here for full text