Title
CHANGE ORDER NO. 02: $798,585.02
SEWARD PARK FIELDHOUSE RESTORATION
FRIEDLER CONSTRUCTION COMPANY
SPECIFICATION NO. P-16008-036
Body
To: The Honorable Board of Commissioners of the Chicago Park District
I. Recommendation
Pursuant to Chapter XI, Section C, 4 of the Code of the Chicago Park District, it is recommended that a change order be approved affecting the contract for the subject work.
II. Award Information
Contractor: Friedler Construction Company
1001 N. Milwaukee, Suite 402
Chicago, IL. 60642
MBE% WBE%
Original Contract Amount: $2,270,800.00 25.41 5.73
Previous Change Orders: $88,694.93 23.27 0.00
Contract Amount prior to this Change Order: $2,359,494.93 25.33 5.51
Amount of Current Change Order: $798,585.02 24.24 6.26
% of the Original Contract: 35%
New Contract Amount: $3,158,079.95 25.06 5.70
Contract Type: Construction Contract
Contract Period: Extended to May 9, 2022
Contract Amount: Not-to-exceed $3,158,079.95
Affirmative Action
Goals: The Minority- and Women-Owned Participation for this contract includes 25% Minority-Owned and 5% Women-Owned.
II. Award Information (Cont.)
Change Order No. 02:
This Change Order includes extensive repair and replacement of deteriorated infrastructure discovered during demolition that wouldn't have been known at the time the construction documents were created until walls and floors were opened up and excavation started w...
Click here for full text