Title: AUTHORIZATION TO ENTER INTO A CONTRACT WITH PAN-OCEANIC ENGINEERING CO. INC. FOR THE LAKE FRONT TRAIL SEPARATION (ARDMORE TO MONTROSE) SPECIFICATION P-15000-186
Sponsors: Planning and Construction
Attachments: 1. P-15000-186 Pan-Oceanic Schedules

Title

AUTHORIZATION TO ENTER INTO A CONTRACT WITH PAN-OCEANIC ENGINEERING CO. INC. FOR THE LAKE FRONT TRAIL SEPARATION (ARDMORE TO MONTROSE)

SPECIFICATION P-15000-186

body

To the Honorable Board of Commissioners of the Chicago Park District

 

I. Recommendation

 

It is recommended that the General Superintendent and CEO or his designee enter into a contract with Pan-Oceanic Engineering Co. Inc. for the construction of the Lakefront Trail Separation from Ardmore Ave. to Montrose Ave.  The contractor was selected pursuant to an Invitation to Bid (IFB) issued to the Rapid Response pre-qualified pool of general contractors.  No work may commence and no payment shall be made to vendor prior to the execution of a written agreement. 

II. Award Information

 

Company:                     Pan Oceanic Engineering Co., Inc.

                     6436 W. Higgins Ave.

                     Chicago, IL 606056

 

Company Type:                                          Business Corporation

 

Majority Interest:                     Gulzar Singh                     100%

 

Contract Term:                     Construction to be completed within 248 days after Notice to Proceed is issued (Estimated to be end of September 2018).

 

Contract Amount:                     Not-to-exceed $2,977,940.00:

 

Scope of Services:                     Scope of work represents the next segment of Lakefront Trail Separation.  The Park District is developing trail separation between bicycle movement and pedestrian movement along Lakefront.  This current section of trail separation work is between Ardmore Ave. and Montrose Ave. approximately 2.25 miles.  The scope of work for this section includes removal of portions of existing Lakefront Trail where necessary, excavation, stone base, new asphalt for bicycle and/or pedestrian trail as needed, new striping and trial markings , seal coating of existing trail sections to remain and trail signage.

 

Affirmative

Action Goals:                       The Minority- and Women-Owned Participation for this contract include: 32% Minority-Owned and 33% Women-Owned.

 

Authorization:                     Authorize the General Counsel to include other relevant terms and conditions in the written Agreement.  Authorize the General Superintendent to execute the Agreement and the Secretary to attest as to the signing of the Agreement and keep an original copy of the Agreement on file.

 

III. Budget and Financial Information

 

Budget Classification:                      Capital and Capital Grant

Fiscal Year:                      2017

Source of Funds:                      351.8260.0100.627030.PG182.16.09.55716

                     31.8260.0100.627030.CP001.01.01.55716

 

IV. Procurement Information

 

Specification Number:                     P-15000-186

Date Issued:                     October 11, 2017

Date of Pre-Submittal Meeting:                     October 16, 2017

Date Proposals Due:                     October 30, 2017

Number of Proposals Received:                     Four (4                     )

 

This contract was bid to the Rapid Response Pre-Qualified pool of General Contractors and an Invitation for Bid (“IFB”) on October 11, 2017.  Four (4) proposals were received on the due date and all proposals were found to be compliant and responsive.