File #: 25-1165-1119    Name: Contract Extension to The Stone Group for Power Rodding and Sewer Cleaning Services
Type: Action Item Status: New Business
File created: 9/12/2025 In control: Board of Commissioners
On agenda: 11/19/2025 Final action:
Title: REQUEST TO EXERCISE THE CONTRACT'S FIRST (1) YEAR EXTENSION OPTION WITH THE STONE GROUP INC. FOR THE SUPPLY AND DELIVERY OF POWER RODDING AND SEWER CLEANING SERVICES-DISTRICT WIDE SPECIFICATION NO. P-23011
Sponsors: Facility Management
Indexes: Contract Extension
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

 

REQUEST TO EXERCISE THE CONTRACT’S FIRST (1) YEAR EXTENSION OPTION WITH THE STONE GROUP INC. FOR THE SUPPLY AND DELIVERY OF POWER RODDING AND SEWER CLEANING SERVICES-DISTRICT WIDE

SPECIFICATION NO. P-23011

 

Body

To:      The Honorable Board of Commissioners of the Chicago Park District

 

I. Recommendation

 

Pursuant to Chapter XI, Section C.3.a of the Code of the Chicago Park District, the Director of Purchasing and the Director of the Department of Facility Management recommend that an order be entered authorizing the General Superintendent or his designee to exercise the first one(1) year extension option with The Stone Group, Inc. for the supply and delivery of power rodding and sewer cleaning services district-wide, Specification No. P-23011.

 

 

II. Initial Award Information

 

Date of Award:                      November 15, 2023 - Chicago Park District Board Meeting                     

 

Contractor:                       The Stone Group, Inc.

                     228 N. Washtenaw Avenue

                     Chicago, IL 60612

 

Company Type:                     Business Corporation

 

Majority Interest:                     Kevin Kenzinger                     100%

                          

Contract Period:                       Two (2) year initial term with three (3) additional one (1) year extension options. The initial term runs from December 29, 2023 with an expiration date of  December 28, 2025. This is the first extension option request. If the extension option is exercised, the effective date will be December 29, 2025 through December 28, 2026. 

 

Contract Amount:                       Not to exceed $289,745.00 for the initial contract term and each extension option. Expenditure for services under the extension term will be authorized by annual appropriation and subject to the year’s budget.

 

Scope of Services:                     Supply and delivery of power rodding and sewer cleaning services-district wide, on an as-needed basis.

 

Authorization:                      Authorize the General Counsel to include other relevant terms and conditions in the written Agreement.  Authorize the General Superintendent to execute the Agreement and the Secretary to attest as to the signing of the Agreement and keep an original copy of the Agreement on file.

 

 

II. Performance to Date:

 

The Stone Group, Inc. has met the expectations under this contract in the first, two-year term to supply and deliver routine and/or emergency power rodding and sewer cleaning services-district wide, on an as-needed basis to the Chicago Park District. Furthermore, they have the capacity to meet the delivery requirements and have done so in a timely and efficient manner for the Chicago Park District and maintained good standing as a vendor.

 

 

III. Current Expenditures: (12/29/2023 - 9/09/2025) Initial Contract Term Start to Date

 

Contract Start Date:                     December 29, 2023

Contract End Date:                     December 28, 2025

 

Spend Amount:                     $281,175 Total

 

Current

Compliance:                     The Minority and Women-Owned Business Enterprise (MBE/WBE) participation achieved during the initial term of the contract was 37% MBE and 5% WBE.

                                                                                    

The percentages shown are against paid contract spend.

 

 

IV. Explanation of Recommendation

 

The Chicago Park District requests approval by the Board to authorize the first, (1) year extension option to The Stone Group, Inc. for a new contract end date of December 28, 2026.

 

The Department of Facility Management is responsible for repairing and maintaining Chicago Park District facilities and parks districtwide and require a company to supply and deliver routine and/or emergency power rodding and sewer cleaning services districtwide, on an as-needed basis.

 

Therefore, it is in the best interest of the Chicago Park District to award The Stone Group, Inc., the first (1) year extension option of the contract for the supply and delivery of power rodding and sewer cleaning services, districtwide.

 

 

V. General Conditions

 

1) Conflicts: The Agreement shall not be legally binding on the Chicago Park District if entered into in violation of the provisions of 50 ILCS 105, the Public Officer Prohibited Activities Act.

 

2) Ethics: The agreement shall contain a provision requiring compliance with Chapter III of the Code of the Chicago Park District (“Governmental Ethics”).

 

3) Contingent Liability:  Any agreement lawfully entered into for a period of more than one year shall be executory only for the amounts for which the Park District may become liable in succeeding fiscal years pursuant to 70 ILCS 1505/17(i).

 

4) Economic Disclosure Statement (“EDS”). Contractor has submitted full and complete EDS.